How long will it take to remodel my space?

January 29, 2017

Time to complete a project varies based on the products being ordered and the scope of work in the remodel. Typical stock production cabinets take about eight days from order to delivery. Semi-Custom cabinets will take 4 to 6 weeks and custom cabinetry will take between 8-12 weeks to deliver. Counter tops are templated and fabricated after cabinets are installed. The top fabrication and installation may take from one to four weeks depending upon the material selected.

Once cabinets are delivered, your contractor or our installers will work to complete a variety of jobs that may include tear out, new drywall construction, electrical, plumbing, tile work, cabinet, flooring and countertop installation as well as other finishing, painting and trim work. Most people plan anywhere from 1 to 6 weeks after delivery of their products to complete their remodel. Your KSI designer will be able to provide a project timeline based on your individual project.